Special developer infrastructure contribution areas

Find out about our special developer infrastructure contribution areas and what contributions may apply to your development.

If your development is located within the areas of Australind, Coral Bay, Denham, or the North east corridor, special developer infrastructure contributions may apply in addition to standard infrastructure contributions. 

Developers of land within the buffer zone of the Australind treatment plant, where a wastewater service is available, are required to pay a special developer infrastructure contribution in addition to standard infrastructure contributions. This is to offset the cost of relocating the wastewater treatment plant.

The contribution is payable on all new lots with sewerage available and is applicable at subdivision stage only.

Infrastructure contributions are not subject to GST.

Payment Period 2017–18
Special developer infrastructure contribution for wastewater $   519
Standard infrastructure contribution for water supply $2,180
Standard infrastructure contribution for wastewater $2,479 

For further details including a map of the area, please refer to our fact sheet.

Australind special developer infrastructure contributions

Developers of residential and commercial properties in Coral Bay are required to pay a special developer infrastructure contribution in addition to a standard infrastructure contribution where a water service is available. The contribution is to offset the cost we incur installing the reticulation pipes required to provide water service connections.

It is payable on all lots with water available and is applicable at building or subdivision stage.

Infrastructure contributions are not subject to GST.

Payment Period 2017–18
Special developer infrastructure contribution for water supply $6,111
Standard infrastructure contribution for water supply $2,180
Standard infrastructure contribution for wastewater $2,479 

For further details including a map of the area, please refer to our fact sheet.

Coral Bay special developer infrastructure contributions

Developers of land in Denham are required to pay a special developer infrastructure contribution as well as the standard infrastructure contribution. This contribution is to offset the costs we incur by installing the infrastructure required to provide these water services.

The contribution is payable on all lots with water available and applies at both subdivision and building stage.

Infrastructure contributions are not subject to GST.

Payment Period 2017–18
Special developer infrastructure contribution for water supply $1,308
Standard infrastructure contribution for water supply $2,180
Standard infrastructure contribution for wastewater $2,479

For further details including a map of the area, please refer to our fact sheet.

Denham special developer infrastructure contributions

Developers in the north east corridor area are required to pay a special developer infrastructure contribution as well as the standard infrastructure contribution to offset the cost of installing the infrastructure required to provide services.

The charge is payable on all new lots with water and wastewater available and is applicable at subdivision stage only.

Infrastructure contributions are not subject to GST.

Payment Period
 2017–18
Special developer infrastructure contribution for water supply $1,921 
Special developer infrastructure contribution for wastewater $2,216
Standard infrastructure contribution for water supply $2,180
Standard infrastructure contribution for wastewater $2,479

For further details including a map of the area, please refer to our fact sheet.

North east corridor special developer infrastructure contributions

More information

For further information about our special developer contribution areas, email us at land.servicing@watercorporation.com.au or call (08) 9420 2099.