Navigate home logo

Project goal:

We are upgrading the Mandurah Gordon Road Water Resource Recovery Facility. These upgrades will cater for future growth in Mandurah and surrounding areas.

Status:

In construction

Delivery:

October 2022 to early 2025  

What's happening?

To cater for growth in Mandurah and surrounds over the next 15 years, we are upgrading the Mandurah Gordon Road Water Resource Recovery Facility (WRRF). These upgrades include:

  • Increasing the plant wastewater treatment capacity from 12 to 15.5 Mega (million) litres per day
  • This will involve the design and construction of new concrete tanks, switchroom, mechanical refurbishment of existing equipment and upgrades to pumps and pipework within the site

Where is this happening?

This work is taking place at the Gordon Road WRRF, which is on the corner of Gordon Road and Mandjoogoordap Drive in Mandurah.  

Why is this taking place?

The WRRF’s capacity is being upgraded to cater for future growth within Mandurah and surrounding districts until 2036. The population is expected to increase by 28,000 people during this time.

When is this happening? 

Construction commenced in October 2022 and is expected to be completed in early 2025.

All work will be at the WRRF site, with limited impact on the community. Work is approved to take place 7am to 7pm Monday to Saturday and 9am to 5pm on Sunday. 

How will this impact the community?  

There will be an increase in noise and activity during construction, however we will do what we can to minimise impacts.  

 
Late October 2024

 

From Tuesday, 29 October 2024 we will be upgrading one of the facilities oxidation ditches. This work is expected to be take approximately one week to complete.

 

An oxidation ditch is shaped like an oval racetrack, it allows bacteria and oxygen to breakdown and remove biodegradable organics from the wastewater.

 

Local residents may notice an increase in truck activity within the facility. This work might also cause a temporary light odour in the immediate area.

 

We apologise for any inconvenience this may cause and thank you for your patience and understanding while we complete this work.


To learn more about the wastewater treatment process please visit our wastewater website.

Early October 2024

Work has been progressing well. The team is currently focused on the commissioning of the newly constructed treatment structures, which include Dissolved Air Flotation Tanks and a Bio-selector.

A Bio-selector mixes the incoming wastewater with active biological microorganisms. These microbes work to remove organic matter.

  Dissolved Air Flotation (DAF) Tanks work to clarify the wastewater by removing suspended matter, such as oils or solids.

To learn more about the wastewater treatment process please visit our wastewater website.

February 2024

The team has recently completed construction of a new concrete storage tank and control room. The upgrades to the pump stations have also been assembled and successfully tested.

In the coming months work will focus on building the remaining concrete structures, installing underground pipe work and conducting electrical work with associated testing.

October 2023

Nearby residents may experience an increase in construction noise. This work began Monday, 30 October 2023 and is scheduled to be completed Wednesday, 1 November 2023. The work will be completed during the working hours of 7am-5pm.

Taylor O’Dea - Community Engagement Advisor

Subscribe for project updates

Information collected on this form will only be used to provide project updates. Privacy policy