Project goal:
We are constructing a new 2.6 km water pipeline to help cater for the continued growth in the City of Cockburn.
Delivery Date:
May 2023 - September 2024
What's happening?
We constructed a new 2.6 km water pipeline along Solomon Road, Dollier Street, Amethyst Street and Greensand Promenade to help cater for the continued growth in the Banjup Urban Precinct.
15 October 2024 update
The installation of the Jandakot and Treeby water pipeline is now complete and operational. Minor reinstatements are still taking place in the area, please seethe table below for more information.
As a token of our gratitude for your patience and understanding during this work, are supporting Treeby Community Association’s annual Halloween-themed Trunk or Treat event on Sunday 27 October 2024. Please visit treebyca.com.au/events for more information.
Where is this happening?
The below map shows the work area.
Why is this taking place?
The Jandakot, Treeby and Banjup areas are currently experiencing high development growth, which requires new infrastructure to service the growing community.
When is this taking place?
Work will usually take place between Monday and Saturday between 7am and 6pm.
Location | Impacts | Timeframe | Map |
Southbound lane of Greensand Promenade, between Solomon Road and Sapphire Drive, in Treeby |
Lane closure |
Monday 21 October Between 9am and 1pm |
Map 1 |
Southbound lane of Solomon Road, between Greensand Promenade and Dollier Street | Lane closure | Monday 21 October from 1pm for approximately one week | Map 2 |
Solomon Road and Armadale Road intersection | Road closure | Monday 28 October for approximately one week. The road will be open over the weekend. | Map 3 |
Amethyst Street and Clementine Boulevard intersection | Road closure | Monday 4 November for approximately one week | Map 4 |
Linemarking along Solomon Road, Greensand Promenade and the intersection of Clementine and Amethyst Street | To be confirmed | To be confirmed |
How will this impact the community?
As with any construction activities there will be an increase in noise, dust and activity in the area. There will also be temporary impacts to roads, verges and pedestrian paths.
We follow a thorough reinstatement process to ensure all impacted areas are replaced like for like, where practically possible. We will also work closely with the City of Cockburn, businesses and residents to ensure all reinstatements are carried out to an acceptable and high standard.
Lexie Naylor – Community Engagement Advisor
General enquiries and feedback
Community Engagement Team
community.engagement@watercorporation.com.au
24 hour Faults, Emergencies and Security Line
13 13 75